Important Property Notices

The following Notices Below are for complexes that have current upcoming or ongoing construction/repairs at the complex or property.

For Addtional questions or concerns please email Knutsonreservations@gmail.com

Kona Makai

Starting September 15 2025 Kona Makai will be starting building 1 on the south side for spalling & painting repairs. 

Work will be done between 7:00 am – 5:00 pm Monday-Friday. 

Unit to be affected in building 1 is 1-301 

Once the building 1 repairs are complete, the scaffold and shoring will be dismantled. McIvor Construction will move the shoring materials to the lanais of units 6-101, 6-201, and 6-301. McIvor will set up their own scaffold and then Atlas Sales will have their crew install the shoring posts and beams on the lanais. McIvor Construction estimates one to two months for the spalling repairs on building 6. As progress is made McIvor Construction will begin to schedule the painting of building 6.

 

Currently they are estimating between 1.5 - 2 Months to complete each building for this work. 

Their current order for the painting of the  buildings mentioned below with the possible affected dates. 

South Building 1 9/15/25 - 1/15/26

Building 6 1/15/26 - 3/15/26

The painting and spalling contractor has agreed to take a break from work for Ironman and the Christmas holidays. Work will stop from October 21st-29th for Ironman. Work will stop from December 23rd- January 3rd for the Holidays  

All dates are subject to change and Knutson & Associates has no say or control in if dates are changed. Dates are given by the complex's hired painting vendor.   

The mentioned work will be affecting access to units at possible given times between the work being done on the building. Kona Makai will be sending notices of more specific dates that access will be affected between work hours. We unfortunately cannot provide any given dates for this. Other areas such as lanai access will be affected during times as well. Furthermore the AC will also not be allowed during specific times/dates when the work is going on.  

Noise and obstructed views are also to be expected between the dates mentioned.

 

 

 

 

KONA REEF 

Kona Reef Structural & Resurfacing Project 2026

Kona Reef will undergo major structural and resurfacing work from January 2026 through June 2026. This project is essential to address water damage, corrosion, and deferred maintenance, ensuring the long-term safety and value of the property.

Tenative Schedule Below 

Building - Duration Owner Responsibility Workdays (M-F)

 

Building B -  Jan 2 - Feb 19

Building A - Jan 25th - April 2nd

Building C -  March 30th - April 15

Building D -  Aprl 14th - May 12

Building E - May 12th - May 28

Building F - May 27th - June 18

 

Schedule of no lanai access for the units below. 

Building B our affected units    Affected 3 & 4 drop dates of 1/25 - 2/19  B15  B7      Building A our affected units    Affected 5 & 6 drop dates of 2/16 - 3/12  A34  A12      Affected 7 & 8 drop dates of  3/9 - 4/2  A7

 

What Guests Should Expect:

  • Construction Noise & Dust: Jackhammers, saws, and other equipment will be in use throughout the complex.

  • Lanai Access: Units will temporarily lose lanai access during their building’s spalling stage.

  • Parking: Parking will be restricted at various times as levels undergo repair; alternate parking areas will be designated.

  • Restricted Areas: For safety, access to active construction zones will be limited or denied.

Important Notes:

  • Work is scheduled Monday–Friday, with dates subject to change due to weather or unforeseen repairs.

  • Owners are responsible for informing renters of construction impacts, including noise, scaffolding, and parking limitations.

  • Updates will be provided regularly as the project progresses.

 

We appreciate your understanding as this necessary work is completed to preserve and enhance Kona Reef.

 

CASA DE EMDEKO  

Notice: Please be advised that the tentatively scheduled work for this week to replace the lanai at Unit 201 is expected to begin tomorrow, November 19th, with the demolition of the deck surface. This work will create noise during weekdays between the hours of 8am to 5pm. No work will be done on weekends or on the 4-day Thanksgiving holiday. The earliest anticipated completion date is Friday, December 5th, if all goes as planned. Updates will be provided as the project progresses.

 

NOTICE: Temporary AC System Shutdown

Please note that the entire chiller system replacement has been rescheduled to begin at 8:00 AM on Monday, November 24th.

During this time, the lines will be drained and flushed, a process that typically takes about half a day. Once complete, the system will be refilled and restarted.

We expect the air conditioning to be fully operational again by 3:00 PM at the latest.

 

 

NOTICE: ELECTRICAL SYSTEM SHUTDOWN

The replacement of the electrical switchgear has been rescheduled to the week of May 11, 2026.

Power will be shut off starting Tuesday, May 12, 2026, at 8:00 AM and is expected to last 48–72 hours.

 

Reminders will be sent as the date approaches. Thank you for your cooperation.

 

 

 

KONA PACIFIC 

Notice: Kona Pacific will undergo Spalling repairs along the south side of buildings B & C, starting on February 3, 2026, with estimated completion on February 10th.

 

Notice: The pool area will be closed from February 10, 2026, through approximately February 20th for flagstone/deck repairs.

What Guests Should Expect:

Construction Noise: Jackhammers, and other equipment will be in use during the dates above.

Keauhou Punahele 

Keauhou Punahele AOAO has contracted with West Hawaii Excavating (WHE) to install a new

sewer line along the west side of our property. We want to let all homeowners know in advance

that this work will be significant. WHE will need to clear a swath of vegetation 8’-12’ wide to install

the line. They will use an excavator/backhoe to dig a trench from 3’-6’ deep to lay the pipe. We

expect to run into large lava boulders or intact lava and will have to use a pneumatic rock hammer

to break this down to manageable sizes.

It will be noisy at times. There will be heavy equipment running, vibration, open trenches, gravel

hauling, and we will be closing-off areas that you may be used to using day to day. These

inconveniences are necessary for us to achieve the goal of a new reliable sewer line. We ask for all

homeowners and their guests to please anticipate these conditions, be patient, and comply with

all signage, flagging, roped off areas, etc.

Kona Isle 

Notice:

Please be advised that Benchmark Construction will begin repairs on the stairwell

located on the west (makai) end of the C Building on Monday, November 24th.

This stairwell will be closed for approximately 2–3 weeks.

Guests staying in the E Building and entering from the parking lot will need to use

the alternate route around the B Building. Work hours will be 8:00 AM to 5:00 PM,

Monday through Friday, with no weekend work scheduled.

KONA PLAZA 

 

Pool Closed 12/23/25- 1/9/26
We are sorry to announce the pool will continue to be closed, Tuesday December 23, 2025 to Friday January 9, 2026, due to re-construction of the pool ramp. We had a strict schedule for re-opening, unfortunately we had unforeseen repairs that must be completed to ensure the ramp is built properly.

Alii Cove – Upcoming Spalling Repair Project Notice

Please be advised that spalling repair work is scheduled to begin at Alii Cove on or around January 5, 2026.

Two separate contractors will be working simultaneously on different buildings throughout the complex:

  • Contractor One will begin with the CC Building, followed by the EE and GG Buildings.

  • Contractor Two will begin with the Q Building, followed by the S and V Buildings.

Although work may not be actively occurring on your specific building at all times, construction-related noise should be expected throughout the community during the project.

At this time, there is no fixed schedule, as the duration of repairs for each building will vary based on the extent of work required. In general, work will not take place in back lanai areas unless a visible issue is identified.

All 35 remaining buildings within the complex are expected to require some level of repair.

At this time, it is anticipated that the entire project will be completed in under 18 months.

We appreciate your understanding and patience during this important maintenance project.