Important Property Notices

The following Notices Below are for complexes that have current upcoming or ongoing construction/repairs at the complex or property.

For Addtional questions or concerns please email Knutsonreservations@gmail.com

 

Alii Villas

 

 

Spalling repairs are to commence at Alii Villas. The scheduled dates for 2024. Noise disruption may happen during working hours. 

Work on building D will begin July 8th and will be brief lasting only about 1 1/2 weeks or less. There are 2 units needing repairs, 327 and 228. All common area spalls will be completed beforehand in-house.
Work on building G will begin July15th and end the last week of July. Units 118 and 320.
Work on building E will begin the last week of July. There are multiple areas of spalling on that building. Mostly on the lanai areas. Units 133,134,136,234,235,334 and a few areas on the posts and beams under the building. Work will continue until completion on or before September 12th. All in-house repairs will be completed by mid August.

Work on building F will begin mid August and will continue for about 3 weeks. Units 241, 242, 337.

Kona Makai

Starting July 22nd Kona Makai will be starting the exterior painting project on Building 4.

Currently they are estimating between 1.5 - 2 Months to complete each building for this work. 

Their current order for the painting of the  buildings mentioned below with the possible affected dates. 

Building 4 7/22 - 9-22  

Building 5 9/22 - 11/22 

Building 3 11/22 - 1/22   

All dates are subject to change and Knutson & Associates has no say or control in if dates are changed. Dates are given by the complex's hired painting vendor.   

The mentioned work will be affecting access to units at possible given times between the work being done on the building. Kona Makai will be sending notices of more specific dates that access will be affected between work hours. We unfortunately cannot provide any given dates for this. Other areas such as lanai access will be affected during times as well. Furthermore the AC will also not be allowed during specific times/dates when the work is going on.  

Noise and obstructed views are also to be expected between the dates mentioned. 

 Spalling repairs are to commence at Kona Makai on Building 1, 2, & 3. The scheduled dates for this are September. Their is currently no completion time for this project. 

 

Country Club Villas   

 

Country Club Villlas will be working on stacks 15 and 16 for steel work sometime between July 29th and August

5th. which will affect units 316 and 115. They will also be doing painting of the railings. This is

estimated between August 12th and 19th. 

During this entire process you will continue to have access to the Unit.

 

Kona Palms

The pool at Kona Palms will be closed on Wednesday, May 1st 2024 through approximately Saturday, June 15th 2024. The pool will be closed due to repairs.