Important Property Notices

The following Notices Below are for complexes that have current upcoming or ongoing construction/repairs at the complex or property.

For Addtional questions or concerns please email Knutsonreservations@gmail.com

KONA REEF 

Plaza Deck (Building F)

November 2–12: Phase 2 surface preparation and waterproofing

November 13 – December 23: Concrete repair. All upper-level parking stalls will be closed 24/7 during this work.

Limited parking: With the entire upper parking level closed, parking at the complex will be limited during this time. Owners who rent their units should let guests know before they arrive so they can plan accordingly.

Please be aware that Building F and the pool area may be heavily affected by noise until the holiday break begins on December 23. The Board is looking for a safe way to keep the heavy jackhammering noise from carrying over to the pool area during this phase.

 January 2,2027 – MARCH 1, 2027

The remaining upper parking work (painting, waterproofing, and demobilization) will continue after the holiday break. We are working to avoid extensive noise from December 24 through March 1 

 MARCH – JUNE 2027

Upper Parking: Remaining work expected to finish by April 1
Lower Parking: April 2 – June 18 (mobilization, survey, concrete repair, painting, and demobilization)
Exterior painting of the entire complex, gutter replacement, and roof recoating: scheduled after high season to minimize the impact on owners and guests. This work will be done by separate new contractors, and we will share their schedules as we receive them.

Expect continued noise around Building F while the parking structure work is underway. We are still hoping to complete all work for the complex by June 2027, as scheduled.

NOT YET SCHEDULED

The Board has identified additional spalling repair needed in the garden area and on the mountain (mauka) side of Building F. This work was not part of the original project scope. The work will show on the schedule in the next few weeks and is not expected to extend the contract beyond the June 28, 2027 completion date. We'll share updates as this is finalized.

 

Alii Cove – Upcoming Spalling Repair Project Notice Posted Dec 9, 2025

Please be advised that spalling repair work is scheduled to begin at Alii Cove on or around January 5, 2026.

Two separate contractors will be working simultaneously on different buildings throughout the complex:

  • Contractor One will begin with the CC Building, followed by the EE and GG Buildings.

  • Contractor Two will begin with the Q Building, followed by the S and V Buildings.

Although work may not be actively occurring on your specific building at all times, construction-related noise should be expected throughout the community during the project.

At this time, there is no fixed schedule, as the duration of repairs for each building will vary based on the extent of work required. In general, work will not take place in back lanai areas unless a visible issue is identified.

All 35 remaining buildings within the complex are expected to require some level of repair.

At this time, it is anticipated that the entire project will be completed in under 18 months.

We appreciate your understanding and patience during this important maintenance project.